Caltrans Logo

Fairfield DART Paratransit Replacement Vehicles

Description: Project is to replace 2 paratransit vehicles for the Fairfield/Suisun DART paratransit service

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield
Zip Code 94533
 
Senate District
05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GEORGE K. FINK (707) 428-7768   GFINK@CI.FAIRFIELD.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $4 $4
PTMISEA-99313
$42 $0 $42
PTMISEA-99314
$68 $0 $68
Non-bond Funding
Local**
$0 $31 $31
 
Total**** $110 $34 $144

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$110 $34 $144 $144 $144 $0
 
Total* $110 $34 $144 $144 $144 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/31/2009 

06/30/2009 
10/11/2011 

10/11/2011 
07/01/2010 

11/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
08/31/2009 

09/30/2009 
03/06/2012 

10/11/2011 
12/01/2010 

06/01/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$109,621
Current Approved:
$113,319
Actual Expenditures:
$113,319

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31