GGBHTD Asset Management and Vehicle Fluid Management Systems

Description: Project is to purchase an Asset / Vehicle Fluid Management System to assisst Maintenance Operations

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94129
 
Senate District
03, 08
Assembly District 12, 13
Congressional District 06, 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GAYLE S. PRIOR (415) 923-2372   GPRIOR@GOLDENGATE.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$2,164 $-350 $1,814
Non-bond Funding
State/Federal*
$2,834 $-47 $2,787
 
Total**** $4,998 $-397 $4,601

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,998 $-397 $4,601 $4,601 $4,601 $0
 
Total* $4,998 $-397 $4,601 $4,601 $4,601 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/31/2009 

12/31/2009 
 

 
01/31/2009 

12/31/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
10/11/2011 

03/02/2012 
11/01/2010 

03/31/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$2,163,666
Current Approved:
$1,814,069
Actual Expenditures:
$1,814,069

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31