SFMTA Persia Triangle Improvements

Description: Project to complete bus stop and circulation improvements in the S.F. Excelsior neigborhood

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
08
Assembly District 12
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  31      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL C. GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$803 $-144 $659
Non-bond Funding
Local**
$0 $640 $640
 
Total**** $803 $496 $1,299

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$127 $-127 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$676 $623 $1,299 $1,299 $1,299 $0
 
Total* $803 $496 $1,299 $1,299 $1,299 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/28/2009 

03/31/2009 
04/20/2010 

06/06/2012 
03/01/2010 

05/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/31/2009 

12/31/2009 
06/06/2012 

09/09/2014 
06/01/2012 

08/01/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2010 

06/30/2011 
09/09/2014 

09/09/2014 
01/01/2015 

12/31/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2011 

12/31/2011 
09/09/2014 

03/10/2015 
01/30/2016 

12/01/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 31

Bond Funding Cost
Adopted:
$802,734
Current Approved:
$659,198
Actual Expenditures:
$659,198

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31