Green Light Rail Center Track Replacement

Description: Replace aprox 11,200 track feet of worn rails and track switches at the north and south ladder track in the Green Facility where SFMTA stores LR vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
12, 13
Assembly District 03, 08
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1      
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL C GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$4,000 $-4,000 $0
Non-bond Funding
State/Federal*
$0 $27,184 $27,184
Local**
$0 $3,175 $3,175
 
Total**** $4,000 $26,359 $30,359

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $4,560 $4,560 $0 $0 $4,560
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,000 $21,799 $25,799 $587 $587 $25,212
 
Total* $4,000 $26,359 $30,359 $587 $587 $29,772

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2009 

10/31/2011 
 

 
10/01/2009 

10/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/31/2011 

12/31/2013 
04/05/2013 

04/05/2013 
01/13/2013 

04/30/2017 
 

 


Begin Closeout Phase

End Closeout Phase
12/31/2013 

12/31/2014 
04/05/2013 

04/05/2013 
05/31/2017 

04/30/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31