BART Pittsburgh / Bay Point Station Improvements

Description: Project is to fund improved lighting and provide real time information at the BART Pittsburgh / Bay Point Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Oakland
Zip Code 94604
 
Senate District
07
Assembly District 11
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MICHAEL TANNER (510) 464-6433   MTANNER@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$320 $0 $320
Non-bond Funding
Local**
$80 $0 $80
 
Total**** $400 $3 $403

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$128 $-108 $20 $0 $0 $20
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$272 $111 $383 $379 $379 $5
 
Total* $400 $3 $403 $379 $379 $25

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2009 

07/01/2009 
04/30/2015 

04/30/2015 
11/01/2008 

03/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2011 

06/01/2011 
04/30/2015 

04/30/2015 
07/30/2012 

12/16/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2011 

12/01/2011 
04/30/2015 

04/30/2015 
01/01/2013 

04/01/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 5

Bond Funding Cost
Adopted:
$320,000
Current Approved:
$320,000
Actual Expenditures:
$320,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31