Caltrans Logo

City of Vallejo Bus Maintenance Facility Repair

Description: Project will repair and rehabilitate the Vallejo 1850 Broadway Street bus maintenance facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Vallejo
Zip Code 94590
 
Senate District
02
Assembly District 07
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Kristina Botsford (707) 648-4046   kristina@soltransride.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $164 $164
PTMISEA-99313
$0 $2,598 $2,598
PTMISEA-99314
$1,557 $248 $1,805
Non-bond Funding
State/Federal*
$728 $2,891 $3,619
Local**
$0 $1,872 $1,872
 
Total**** $2,285 $7,773 $10,058

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,285 $7,773 $10,058 $10,058 $10,058 $0
 
Total* $2,285 $7,773 $10,058 $10,058 $10,058 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/18/2010 

03/18/2010 
02/28/2010 

04/30/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/31/2009 

03/31/2010 
07/24/2014 

10/11/2017 
03/01/2009 

08/31/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
10/11/2017 

10/11/2017 
09/01/2017 

09/30/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$1,556,825
Current Approved:
$4,403,047
Actual Expenditures:
$4,403,047

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31