Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
City of Vallejo Bus Maintenance Facility Repair |
Description: Project will repair and rehabilitate the Vallejo 1850 Broadway Street bus maintenance facility
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Solano |
City | Vallejo |
Zip Code | 94590 |
Senate District |
02 |
Assembly District | 07 |
Congressional District | 07 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 15 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Kristina Botsford | (707) 648-4046 | kristina@soltransride.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $164 | $164 | ||||
PTMISEA-99313 |
$0 | $2,598 | $2,598 | ||||
PTMISEA-99314 |
$1,557 | $248 | $1,805 | ||||
Non-bond Funding | |||||||
State/Federal* |
$728 | $2,891 | $3,619 | ||||
Local** |
$0 | $1,872 | $1,872 | ||||
Total**** | $2,285 | $7,773 | $10,058 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,285 | $7,773 | $10,058 | $10,058 | $10,058 | $0 | |
Total* | $2,285 | $7,773 | $10,058 | $10,058 | $10,058 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
03/18/2010 03/18/2010 |
02/28/2010 04/30/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/31/2009 03/31/2010 |
07/24/2014 10/11/2017 |
03/01/2009 08/31/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
10/11/2017 10/11/2017 |
09/01/2017 09/30/2017 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 15 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,556,825 |
Current Approved: |
$4,403,047 |
Actual Expenditures: |
$4,403,047 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31