Loomis Bus Stop Improvements

Description: Improve three bus shelters by adding safe pull out for the buses and all weather surface between the bus shelter and the roadway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4090   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$23 $0 $23
Non-bond Funding
Local**
$2 $-2 $0
 
Total**** $25 $-2 $23

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $-1 $0 $0 $0 $0
Design(PS&E)
$8 $-4 $4 $4 $4 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$16 $4 $20 $20 $20 $0
 
Total* $25 $-2 $23 $23 $23 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
01/01/2009 

02/01/2009 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
02/01/2009 

05/01/2009 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
07/01/2009 

10/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
08/17/2009 

08/25/2009 
11/01/2009 

12/31/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1

Bond Funding Cost
Adopted:
$23,103
Current Approved:
$23,103
Actual Expenditures:
$23,103

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31