South Perris Parking Lot

Description: Replacing and repairing the South Perris Parking Lot

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92501
 
Senate District
31
Assembly District 60
Congressional District 39
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ERIC DEHATE (951) 453-6765   EDEHATE@RCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $65 $65
PTMISEA-99313
$363 $-1 $362
Non-bond Funding
State/Federal*
$1,418 $0 $1,418
 
Total**** $1,781 $64 $1,845

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,781 $64 $1,845 $0 $0 $1,845
 
Total* $1,781 $64 $1,845 $0 $0 $1,845

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2023 

06/30/2023 
 

 
04/15/2023 

06/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2023 

08/31/2023 
 

 
06/30/2023 

08/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 5

Bond Funding Cost
Adopted:
$363,270
Current Approved:
$362,270
Actual Expenditures:
$362,270

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31