CNG Transit Bus Purchase

Description: 1 HEAVY DUTY TRANSIT CNG BUS

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  12    10  
Reduced Operating/Maintenance Cost  10    17  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LINDA CLARK (559) 782-4886   LCLARK@CI.PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$225 $0 $225
PTMISEA-99314
$17 $0 $17
Non-bond Funding
Local**
$0 $178 $178
 
Total**** $242 $180 $422

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$242 $180 $422 $422 $422 $0
 
Total* $242 $180 $422 $422 $422 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2009 

03/31/2010 
02/15/2011 

02/15/2011 
07/30/2009 

09/13/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2010 

05/31/2010 
02/15/2011 

02/15/2011 
11/01/2010 

11/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 12 10
Reduced Operating/Maintenance Cost 10 17

Bond Funding Cost
Adopted:
$241,943
Current Approved:
$241,943
Actual Expenditures:
$241,943

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31