Imperial Valley College Bus Transfer Terminal (Phase II)

Description: Phase II of the Imperial Valley College Bus Transfer Terminal

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City El Centro
Zip Code 92243
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHI WILLIAMS (760) 482-4290   KATHIWILLIAM@CO.IMPERIAL.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $59 $59
PTMISEA-99313
$900 $21 $920
Non-bond Funding
State/Federal*
$133 $0 $133
Local**
$377 $-377 $0
 
Total**** $1,410 $-297 $1,112

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$185 $-169 $16 $16 $16 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,225 $-129 $1,096 $1,096 $1,096 $0
 
Total* $1,410 $-297 $1,112 $1,112 $1,112 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2008 

04/01/2008 
 

 
03/01/2008 

04/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

05/01/2009 
 

08/26/2011 
01/01/2009 

09/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2009 

11/01/2009 
08/26/2011 

08/26/2011 
07/31/2011 

04/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2010 

02/01/2010 
09/04/2012 

09/04/2012 
08/01/2012 

09/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 2

Bond Funding Cost
Adopted:
$899,616
Current Approved:
$920,161
Actual Expenditures:
$920,161

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31