Transit Maintenance/Bus Cover Facility - Lincoln

Description: Install covered bus facility adjacent to the new Corporation Yard; concrete parking, drainage systems, lighting & fencing

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn, Ca
Zip Code 95603
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4090   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$19 $139 $158
PTMISEA-99314
$0 $1 $1
Non-bond Funding
State/Federal*
$0 $534 $534
Local**
$0 $35 $35
 
Total**** $19 $708 $727

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$19 $0 $19 $19 $19 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $708 $708 $708 $708 $0
 
Total* $19 $708 $727 $727 $727 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
03/27/2012 

03/27/2012 
08/01/2006 

04/01/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/27/2012 

03/27/2012 
07/01/2008 

07/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2010 

06/30/2010 
03/27/2012 

03/27/2012 
02/01/2010 

11/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

09/30/2010 
03/27/2012 

03/27/2012 
10/01/2010 

02/01/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$19,246
Current Approved:
$159,221
Actual Expenditures:
$159,221

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31