Caltrans Logo

Auburn Transit Bus Shelter

Description: Construct bus shelter on Auburn Ravine at Persimmon Terrace

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn, Ca
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4030   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$11 $0 $11
Non-bond Funding
Local**
$1 $-1 $0
 
Total**** $12 $-1 $11

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$12 $-1 $11 $11 $11 $0
 
Total* $12 $-1 $11 $11 $11 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2010 

08/01/2010 
 

10/01/2010 
06/01/2010 

08/01/2010 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2010 

04/01/2011 
09/01/2010 

09/01/2010 
01/01/2011 

02/18/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2011 

06/01/2011 
09/01/2011 

10/31/2011 
05/01/2011 

06/01/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 2

Bond Funding Cost
Adopted:
$11,030
Current Approved:
$11,030
Actual Expenditures:
$11,030

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31