La Sierra Station Parking Lot Expansion |
Description: Expanded parking to add approximately 500 spaces
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside |
Zip Code | 92501 |
Senate District |
31 |
Assembly District | 66 |
Congressional District | |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
SHELDON PETERSON | (951) 787-7928 | SPETERSON@RCTC.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$871 | $-803 | $68 | ||||
Non-bond Funding | |||||||
Local** |
$1,587 | $-1,587 | $0 | ||||
Total**** | $2,458 | $-2,390 | $68 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $-32 | $68 | $68 | $68 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,358 | $-2,358 | $0 | $0 | $0 | $0 | |
Total* | $2,458 | $-2,390 | $68 | $68 | $68 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/01/2009 04/01/2009 |
|
03/01/2009 04/01/2009 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2009 09/01/2009 |
03/22/2011 |
04/01/2009 04/01/2011 |
90 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2009 04/01/2010 |
09/10/2012 09/10/2012 |
11/30/2011 11/30/2011 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2010 05/01/2010 |
09/10/2012 09/10/2012 |
11/30/2011 11/30/2011 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$870,637 |
Current Approved: |
$67,780 |
Actual Expenditures: |
$67,780 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31