La Sierra Station Parking Lot Expansion

Description: Expanded parking to add approximately 500 spaces

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92501
 
Senate District
31
Assembly District 66
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SHELDON PETERSON (951) 787-7928   SPETERSON@RCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$871 $-803 $68
Non-bond Funding
Local**
$1,587 $-1,587 $0
 
Total**** $2,458 $-2,390 $68

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $-32 $68 $68 $68 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,358 $-2,358 $0 $0 $0 $0
 
Total* $2,458 $-2,390 $68 $68 $68 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2009 

04/01/2009 
 

 
03/01/2009 

04/01/2009 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2009 

09/01/2009 
 

03/22/2011 
04/01/2009 

04/01/2011 
90   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2009 

04/01/2010 
09/10/2012 

09/10/2012 
11/30/2011 

11/30/2011 
 

 


Begin Closeout Phase

End Closeout Phase
04/01/2010 

05/01/2010 
09/10/2012 

09/10/2012 
11/30/2011 

11/30/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1

Bond Funding Cost
Adopted:
$870,637
Current Approved:
$67,780
Actual Expenditures:
$67,780

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31