35' Coach Replacement

Description: Purchase of two replacement 35-foot transit coaches.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Banning
Zip Code 92220
 
Senate District
37
Assembly District 65
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  40      
Increased Ridership  20    5  
Reduced Operating/Maintenance Cost  40    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
HEIDI MERAZ (951) 922-3241   HMERAZ@CI.BANNING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$214 $653 $867
PTMISEA-99314
$11 $4 $16
Non-bond Funding
 
Total**** $225 $662 $888

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$225 $662 $888 $888 $888 $0
 
Total* $225 $662 $888 $888 $888 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

08/01/2015 
05/27/2020 

05/27/2020 
03/04/2016 

09/12/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/01/2015 
05/27/2020 

05/27/2020 
10/25/2016 

10/25/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 40
Increased Ridership 20 5
Reduced Operating/Maintenance Cost 40 5

Bond Funding Cost
Adopted:
$225,452
Current Approved:
$882,299
Actual Expenditures:
$882,299

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31