Caltrans Logo

Transit Facility

Description: Construction of an operations office centralizing all operational departments, storage of vehicles, and supplies.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Blythe
Zip Code 92225
 
Senate District
40
Assembly District 80
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30    30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
HELEN COLBERT (760) 921-2340   HCOLBERT@CITYOFBLYTHE.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$377 $54 $431
PTMISEA-99314
$15 $29 $43
Non-bond Funding
State/Federal*
$325 $-0 $325
 
Total**** $717 $84 $801

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $21 $21 $-21
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$717 $84 $801 $455 $455 $346
 
Total* $717 $84 $801 $476 $476 $325

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/16/2009 

04/01/2009 
04/24/2012 

04/12/2011 
06/01/2010 

07/01/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/15/2009 

06/01/2009 
04/12/2011 

10/19/2012 
07/01/2010 

12/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

07/01/2009 
04/12/2011 

04/12/2011 
01/01/2010 

07/01/2010 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2009 

09/01/2009 
03/25/2014 

03/17/2015 
03/01/2014 

12/08/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30 30

Bond Funding Cost
Adopted:
$391,785
Current Approved:
$474,262
Actual Expenditures:
$474,262

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31