Caltrans Logo

Metrolink Positive Train Control

Description: Positive train control to meet the requirements of Federal legislation.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92401
 
Senate District
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38
Assembly District 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE BAIR (909) 884-8276   MBAIR@SANBAG.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $228 $228
PTMISEA-99313
$3,310 $0 $3,310
PTMISEA-99314
$13,664 $303 $13,966
Non-bond Funding
State/Federal*
$67,810 $130,848 $198,658
Local**
$130,486 $-97,356 $33,130
 
Total**** $215,269 $34,023 $249,292

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$22,206 $-22,206 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$193,063 $56,229 $249,292 $249,292 $249,292 $0
 
Total* $215,269 $34,023 $249,292 $249,292 $249,292 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2008 

04/30/2009 
 

 
12/01/2008 

04/30/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/15/2009 

06/30/2012 
02/15/2011 

04/10/2023 
10/15/2010 

03/31/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2012 

12/30/2012 
04/10/2023 

12/08/2023 
04/01/2023 

04/30/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5

Bond Funding Cost
Adopted:
$16,973,066
Current Approved:
$17,275,617
Actual Expenditures:
$17,275,617

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31