Blue Line Light Rail Vehicle Purchase

Description: Blue Line Light Rail Vehicle Purchase

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code 92122
 
Senate District
36, 39, 40
Assembly District 75, 76, 77, 78, 79
Congressional District 50, 51, 52, 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      6  
Increased Ridership  6    6  
Reduced Operating/Maintenance Cost      10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SOOKYUNG KIM (619) 699-6909   SKI@SANDAG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$30,609 $0 $30,609
PTMISEA-99314
$10,788 $0 $10,788
Non-bond Funding
State/Federal*
$31,097 $0 $31,097
Local**
$197,235 $-136,347 $60,888
 
Total**** $269,729 $-136,346 $133,383

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$269,729 $-136,346 $133,383 $133,383 $133,383 $0
 
Total* $269,729 $-136,346 $133,383 $133,383 $133,383 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/09/2009 

11/09/2009 
 

08/03/2012 
10/09/2009 

06/03/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2013 

12/01/2014 
01/29/2015 

01/29/2015 
08/31/2013 

04/30/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 6
Increased Ridership 6 6
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$41,397,075
Current Approved:
$41,397,075
Actual Expenditures:
$41,397,075

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31