Description: Construction of a new ACE equipment maintenance facility
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95202 |
Senate District |
17 |
Assembly District | 05 |
Congressional District | |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
BRIAN SCHMIDT | (209) 944-6241 | BRIAN@ACERAIL.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $6 | $6 | ||||
PTMISEA-99313 |
$1,276 | $0 | $1,276 | ||||
PTMISEA-99314 |
$104 | $0 | $104 | ||||
Non-bond Funding | |||||||
State/Federal* |
$25,632 | $4,943 | $30,575 | ||||
Local** |
$16,987 | $27,730 | $44,717 | ||||
Total**** | $43,999 | $32,679 | $76,678 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,112 | $-1,126 | $986 | $985 | $985 | $1 | |
Right of Way |
$4,900 | $4,500 | $9,400 | $9,400 | $9,400 | $0 | |
Construction |
$36,987 | $29,305 | $66,292 | $20,361 | $20,361 | $45,931 | |
Total* | $43,999 | $32,679 | $76,678 | $30,746 | $30,746 | $45,932 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2003 12/31/2008 |
|
06/01/2003 12/31/2008 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2003 11/30/2010 |
|
06/01/2003 11/30/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/31/2011 10/31/2012 |
|
08/01/2011 10/31/2013 |
41 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/31/2010 03/31/2011 |
|
10/31/2013 12/31/2013 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,379,864 |
Current Approved: |
$1,379,864 |
Actual Expenditures: |
$1,379,864 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31