Purchase & Install Local Fareboxes

Description: Purchase & Install Local Fareboxes for the transit buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Lodi
Zip Code 95241
 
Senate District
10
Assembly District 14
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30      
Increased Ridership      18  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PAULA FERNANDEZ (209) 333-6800 X2667   PFERNANDEZ@LODI.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$60 $0 $60
Non-bond Funding
 
Total**** $60 $1 $61

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$60 $1 $61 $61 $61 $0
 
Total* $60 $1 $61 $61 $61 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2010 

08/31/2010 
02/29/2012 

03/05/2013 
09/30/2011 

11/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2010 

03/31/2011 
03/05/2013 

03/05/2013 
11/30/2012 

12/31/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Increased Ridership 18

Bond Funding Cost
Adopted:
$60,000
Current Approved:
$60,800
Actual Expenditures:
$60,800

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31