Regional Operations Facility (Parcel II)

Description: Purchase Right of Way to use for Regional Operations Facility for Parcel II

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05, 14
Assembly District 15, 17, 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  230      
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566 X613   DDMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$876 $0 $876
Non-bond Funding
State/Federal*
$4,680 $-3,017 $1,663
Local**
$6,000 $-5,214 $786
 
Total**** $11,556 $-8,231 $3,325

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,904 $-2,904 $0 $0 $0 $0
Right of Way
$3,032 $293 $3,325 $3,325 $3,325 $0
Construction
$6,000 $-6,000 $0 $0 $0 $0
 
Total* $11,556 $-8,231 $3,325 $3,325 $3,325 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2009 

04/01/2010 
 

10/05/2010 
03/01/2009 

08/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2009 

02/01/2010 
 

10/05/2010 
03/01/2009 

03/01/2010 
100   

 


Begin Construction Phase

End Construction Phase
01/01/2010 

04/01/2012 
10/05/2010 

 
12/01/2010 

04/01/2012 
 

 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

06/01/2012 
 

 
06/01/2012 

06/01/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 230
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$875,883
Current Approved:
$875,883
Actual Expenditures:
$875,883

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31