Las Tablas Park&Ride Expansion

Description: Addition of 24 parking spaces at Park&Ride lot in Templeton, CA

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City San Luis Obispo
Zip Code 93408
 
Senate District
15
Assembly District 33
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  36    36  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVE FLYNN (805) 781-4463   DFLYNN@CO.SLO.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$75 $0 $75
PTMISEA-99314
$1 $0 $1
Non-bond Funding
Local**
$0 $151 $151
 
Total**** $76 $151 $227

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$76 $151 $227 $76 $76 $151
 
Total* $76 $151 $227 $76 $76 $151

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2008 

02/01/2009 
03/25/2011 

03/25/2011 
10/17/2008 

10/29/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2008 

06/01/2009 
03/25/2011 

03/25/2011 
09/22/2008 

09/25/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
10/01/2008 

02/01/2009 
 

 
10/01/2008 

02/01/2009 
100   

 


Begin Construction Phase

End Construction Phase
08/01/2009 

01/01/2010 
03/25/2011 

03/25/2011 
06/21/2010 

08/23/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2010 

03/01/2010 
03/25/2011 

03/25/2011 
09/30/2010 

03/31/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 36 36

Bond Funding Cost
Adopted:
$76,191
Current Approved:
$76,191
Actual Expenditures:
$76,191

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31