Caltrans Logo

RTA Shop Equipment

Description: Shop equipment purchase for new facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City San Luis Obispo
Zip Code 93401
 
Senate District
15
Assembly District 33
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  50    50  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
EDWARD KING (805) 781-4465   EKING@SLORTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$84 $0 $84
Non-bond Funding
Local**
$26 $0 $26
 
Total**** $110 $0 $110

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$110 $0 $110 $84 $84 $26
 
Total* $110 $0 $110 $84 $84 $26

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2009 

06/30/2009 
 

 
05/01/2009 

06/30/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2009 

07/31/2009 
 

 
07/01/2009 

07/31/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 50 50

Bond Funding Cost
Adopted:
$84,216
Current Approved:
$84,216
Actual Expenditures:
$84,216

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31