South Line Phase 2 Light Rail Expansion-Sacramento

Description: Construction of light rail line extension from Meadowview Rd to Cosumnes River College

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento, Ca
Zip Code 95812
 
Senate District
05, 06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      5  
Increased Ridership  6      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DIANE NAKANO (916) 321-3853   DNAKANO@SACRT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $73 $73
PTMISEA-99313
$3,979 $-3,979 $0
PTMISEA-99314
$0 $4,201 $4,201
Non-bond Funding
State/Federal*
$202,604 $-190,047 $12,557
Local**
$44,697 $-44,208 $489
 
Total**** $251,281 $-233,960 $17,320

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$18,302 $-18,302 $0 $0 $0 $0
Design(PS&E)
$5,100 $-792 $4,308 $3,269 $3,269 $1,039
Right of Way
$15,529 $-15,529 $0 $0 $0 $0
Construction
$212,350 $-199,338 $13,012 $13,720 $13,720 $-708
 
Total* $251,281 $-233,960 $17,320 $16,989 $16,989 $331

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
08/01/2012 

08/01/2012 
05/29/2012 

12/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2010 

05/01/2011 
 

02/14/2023 
09/01/2010 

05/31/2023 
98   

 


Begin Closeout Phase

End Closeout Phase
07/01/2013 

07/31/2013 
02/14/2023 

02/14/2023 
06/01/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 6

Bond Funding Cost
Adopted:
$3,979,571
Current Approved:
$4,201,146
Actual Expenditures:
$4,201,146

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31