Expand RABA Downtown Transit Center-Redding

Description: Acquire property adjacent to the RABA Downtown Transit Center for future expansion of the intermodal facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding, Ca
Zip Code 96049
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      25  
Increased Ridership  10      
Reduced Emissions  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ZACH BONNIN (530) 225-4392   ZBONNIN@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,234 $781 $2,016
PTMISEA-99314
$87 $-20 $67
Non-bond Funding
 
Total**** $1,322 $761 $2,082

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$54 $0 $54 $206 $206 $-152
Right of Way
$1,115 $0 $1,115 $463 $463 $652
Construction
$153 $761 $913 $1,414 $1,414 $-501
 
Total* $1,322 $761 $2,082 $2,082 $2,082 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2011 

07/01/2011 
09/02/2014 

09/02/2014 
03/01/2012 

10/01/2014 
 

 


Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

01/01/2011 
06/23/2015 

05/09/2017 
03/01/2015 

12/01/2017 
 

 


Begin Construction Phase

End Construction Phase
09/01/2012 

12/01/2012 
09/02/2014 

09/02/2014 
11/01/2014 

08/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
01/31/2011 

06/30/2011 
08/07/2020 

08/07/2020 
06/01/2020 

06/01/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25
Increased Ridership 10
Reduced Emissions 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$1,321,520
Current Approved:
$2,082,443
Actual Expenditures:
$2,082,443

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31