Caltrans Logo

Replacement of Transit Vehicles

Description: Purchase two ADA compliant transit vehicles for private non-profit providers in Sierra County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sierra
City Downieville
Zip Code 95936
 
Senate District
01
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      50  
Reduced Operating/Maintenance Cost  50      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BRYAN DAVEY (530) 289-3201   BDAVEY@SIERRACOUNTY.WS
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$26 $0 $26
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $26 $0 $26

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$101 $0 $101 $101 $101 $0
 
Total* $26 $0 $26 $101 $101 $-75

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2009 

02/01/2010 
03/13/2012 

03/13/2012 
06/23/2010 

02/03/2011 
 

 


Begin Closeout Phase

End Closeout Phase
02/15/2011 

08/15/2011 
 

 
02/15/2011 

08/15/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Reduced Operating/Maintenance Cost 50

Bond Funding Cost
Adopted:
$25,688
Current Approved:
$25,688
Actual Expenditures:
$25,688

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31