Sutter Hill Transit Center (Phase II)

Description: Construct phase II which includes expanding parking, enhancing the bus transfer facility with additional security and communications systems, also constructing support office offices

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Amador
City Jackson
Zip Code 95642
 
Senate District
01
Assembly District 10
Congressional District 03
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      50  
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT BOYER (916) 858-0642   MBOYER@DOKKENENGINEERING.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$189 $0 $189
PTMISEA-99314
$14 $0 $14
Non-bond Funding
State/Federal*
$789 $56 $845
Local**
$0 $742 $742
 
Total**** $991 $802 $1,793

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$991 $802 $1,793 $1,793 $1,793 $0
 
Total* $991 $802 $1,793 $1,793 $1,793 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

05/01/2009 
 

 
01/01/2009 

05/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2008 

04/15/2009 
 

 
11/01/2008 

04/15/2009 
100   

 


Begin Construction Phase

End Construction Phase
06/15/2009 

06/15/2010 
03/09/2011 

03/09/2011 
04/30/2011 

06/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
06/15/2010 

12/15/2010 
03/09/2011 

08/15/2012 
06/30/2012 

08/15/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Increased Ridership 10

Bond Funding Cost
Adopted:
$202,487
Current Approved:
$202,487
Actual Expenditures:
$202,487

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31