Caltrans Logo

Purchase of ITS Equipment - Chico

Description: Purchase of dispatching & AVL system, bus stop way signs, audio visual enunciators, & LCD info. displays

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Chico, Ca
Zip Code 95928
 
Senate District
01, 04
Assembly District 01, 02
Congressional District 01
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    100  
Increased Ridership      2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MR. ROBIN VAN VALKENBURGH (530) 879-2468   RVANVALKENBURGH@BCAG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $8 $8
PTMISEA-99313
$325 $0 $325
PTMISEA-99314
$12 $0 $12
Non-bond Funding
 
Total**** $337 $8 $345

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$337 $8 $345 $345 $345 $0
 
Total* $337 $8 $345 $345 $345 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/15/2010 

12/01/2010 
05/08/2012 

09/05/2014 
02/01/2010 

12/01/2014 
97   

 


Begin Closeout Phase

End Closeout Phase
01/01/2011 

03/31/2011 
09/05/2014 

09/05/2014 
01/01/2012 

12/01/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 100
Increased Ridership 2

Bond Funding Cost
Adopted:
$337,035
Current Approved:
$337,035
Actual Expenditures:
$337,035

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31