Caltrans Logo

Transit Bus Stop Facilites

Description: Improvements on various bus stop facilites in Calaveras County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Calaveras
City San Andreas
Zip Code 95249
 
Senate District
01
Assembly District 25
Congressional District 03
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MELISSA EADS (209) 754-2094   MEASDS@CALCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$205 $-116 $89
Non-bond Funding
State/Federal*
$0 $172 $172
Local**
$0 $14 $14
 
Total**** $205 $70 $275

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$205 $70 $275 $275 $275 $0
 
Total* $205 $70 $275 $275 $275 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2009 

12/31/2009 
02/29/2012 

09/25/2012 
08/01/2010 

07/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2009 

01/31/2010 
09/25/2012 

09/25/2012 
08/31/2010 

08/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
08/01/2009 

01/31/2010 
09/25/2012 

09/25/2012 
08/31/2010 

02/28/2012 
 

 


Begin Construction Phase

End Construction Phase
03/01/2010 

06/30/2010 
09/04/2014 

09/04/2014 
07/01/2014 

03/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
07/31/2010 

07/31/2010 
05/12/2016 

05/12/2016 
01/01/2016 

03/11/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5

Bond Funding Cost
Adopted:
$205,000
Current Approved:
$89,256
Actual Expenditures:
$89,256

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31