Caltrans Logo

Bus Shelters-Tahoe Basin/El Dorado Co.

Description: Install bus shelters through the BlueGO service area

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Stateline, Nv
Zip Code 89449
 
Senate District
01
Assembly District 04
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  25    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
NICK HAVEN (775) 589-5256   NHAVEN@TRPA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$111 $41 $152
Non-bond Funding
State/Federal*
$0 $242 $242
 
Total**** $111 $283 $395

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$111 $283 $395 $395 $395 $0
 
Total* $111 $283 $395 $395 $395 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
30   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2010 

07/31/2010 
09/02/2011 

03/10/2015 
10/01/2011 

06/30/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2010 

09/30/2010 
03/10/2015 

03/10/2015 
07/01/2014 

12/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 25 25

Bond Funding Cost
Adopted:
$111,325
Current Approved:
$151,842
Actual Expenditures:
$151,842

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31