Caltrans Logo

Purchase/Install CNG Compressor

Description: Purchase and Install a third CNG compressor at FAX main facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93706
 
Senate District
14, 16
Assembly District 31
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  5    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DARLENE CHRISTIANSEN (559) 621-1469   DARLENE.CHRISTIANSEN@FRESNO.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$55 $0 $55
Non-bond Funding
State/Federal*
$493 $0 $493
 
Total**** $548 $6 $554

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$548 $6 $554 $552 $552 $2
 
Total* $548 $6 $554 $552 $552 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
06/02/2014 

06/02/2014 
02/01/2009 

02/28/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2010 

03/31/2011 
09/29/2015 

09/29/2015 
06/01/2016 

10/31/2016 
 

 


Begin Closeout Phase

End Closeout Phase
04/01/2011 

06/30/2011 
09/29/2015 

09/29/2015 
10/31/2016 

11/30/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 5 3

Bond Funding Cost
Adopted:
$54,600
Current Approved:
$60,103
Actual Expenditures:
$60,103

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31