Twelve Bus Purchase

Description: Purchase 12 public transit buses. The breakdown is 7 (40', 41 passenger) and 5 (22', 14 passenger) diesel buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
32
Assembly District 18
Congressional District 20, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      25  
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DENISE HAYNES (661) 862-5078   HAYNESD@CO.KERN,CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$3,789 $-130 $3,659
PTMISEA-99314
$34 $0 $34
Non-bond Funding
 
Total**** $3,824 $-130 $3,694

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,824 $-130 $3,694 $3,654 $3,654 $40
 
Total* $3,824 $-130 $3,694 $3,654 $3,654 $40

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
09/18/2015 

09/18/2015 
03/01/2014 

08/31/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2014 

09/30/2015 
09/18/2015 

09/18/2015 
09/01/2014 

06/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

09/30/2015 
09/18/2015 

09/18/2015 
07/01/2015 

07/31/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$3,823,606
Current Approved:
$3,693,606
Actual Expenditures:
$3,653,790

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31