Purchase a Bus

Description: Purchase a 32-foot type VII gas powered bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Ridgecrest
Zip Code 93555
 
Senate District
18
Assembly District 32
Congressional District 41
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
Reduced Operating/Maintenance Cost  45    45  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANN TAYLOR (760) 499-5006   ATAYLOR@CI.RIDGECREST.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$98 $-8 $90
Non-bond Funding
 
Total**** $98 $-8 $90

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$98 $-8 $90 $90 $90 $0
 
Total* $98 $-8 $90 $90 $90 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2010 

03/31/2012 
09/13/2011 

10/22/2013 
08/01/2011 

07/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
12/11/2011 

09/30/2012 
10/22/2013 

10/22/2013 
12/11/2011 

10/22/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50
Reduced Operating/Maintenance Cost 45 45

Bond Funding Cost
Adopted:
$98,000
Current Approved:
$89,768
Actual Expenditures:
$89,768

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31