Construct Bus Stop and Shelters

Description: Construct accessible bust stop at People's Services and Purchase and install 3 bust stop shelters

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Lake
City Visalia
Zip Code 93277
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MARK WALL (707) 465-6830  
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$50 $0 $50
Non-bond Funding
State/Federal*
$28 $16 $44
 
Total**** $79 $16 $94

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$79 $16 $94 $94 $94 $0
 
Total* $79 $16 $94 $94 $94 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/24/2011 

06/30/2012 
 

 
09/24/2011 

06/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
07/30/2012 

09/30/2012 
09/23/2014 

09/23/2014 
11/01/2011 

03/26/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3

Bond Funding Cost
Adopted:
$50,278
Current Approved:
$50,278
Actual Expenditures:
$50,278

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31