Caltrans Logo

Bus Shelter/Parking Lot Improvements

Description: Construction of transit bus shelter/parking facilities

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 31
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    2  
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD POYTHRESS (559) 675-0721   RICHARD@MADERACTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $222 $222
PTMISEA-99313
$263 $787 $1,050
Non-bond Funding
 
Total**** $263 $1,009 $1,272

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$263 $1,009 $1,272 $1,272 $1,272 $0
 
Total* $263 $1,009 $1,272 $1,272 $1,272 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2010 

06/30/2010 
02/16/2022 

02/16/2022 
03/31/2019 

06/30/2019 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2010 

01/31/2011 
02/16/2022 

02/16/2022 
07/31/2021 

05/31/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2011 

03/31/2011 
02/16/2022 

02/16/2022 
05/31/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 2
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$262,610
Current Approved:
$1,049,888
Actual Expenditures:
$1,049,888

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31