Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Paratransit Vehicle & Equipment Purchase |
Description: Purchase of 90 hybrids, 4 passenger sedans, 4 vans, chargings stations, radio systems
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara |
City | San Jose, Ca |
Zip Code | 95134 |
Senate District |
23 |
Assembly District | 13 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 60 | 56 |
Reduced Operating/Maintenance Cost | 25 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
JEFFERY BALLOU | (408) 321-5628 | JEFFERY.BALLOU@VTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $64 | $64 | ||||
PTMISEA-99313 |
$3,476 | $0 | $3,476 | ||||
PTMISEA-99314 |
$7,637 | $-1,146 | $6,491 | ||||
Non-bond Funding | |||||||
Total**** | $11,113 | $-1,082 | $10,030 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$11,113 | $-1,082 | $10,030 | $10,030 | $10,030 | $0 | |
Total* | $11,113 | $-1,082 | $10,030 | $10,030 | $10,030 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2011 12/31/2011 |
08/27/2014 08/19/2016 |
09/26/2012 09/29/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2012 06/30/2012 |
02/23/2018 08/08/2018 |
12/31/2017 01/31/2018 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 60 | 56 |
Reduced Operating/Maintenance Cost | 25 |
Bond Funding Cost | |
---|---|
Adopted: |
$11,112,650 |
Current Approved: |
$9,966,647 |
Actual Expenditures: |
$9,966,647 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31