Caltrans Logo

40' Hybrid Replacement Bus Procurement

Description: Purchase 40' Hybrid Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95134
 
Senate District
10
Assembly District 25
Congressional District 17
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  20    19  
Reduced Operating/Maintenance Cost  25    84  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFERY BALLOU (408) 321-5628   JEFFERY.BALLOU@VTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$178 $1,226 $1,404
PTMISEA-99314
$2,994 $1,013 $4,007
Non-bond Funding
State/Federal*
$7,390 $0 $7,390
 
Total**** $10,561 $2,240 $12,801

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$10,561 $2,240 $12,801 $12,801 $12,801 $0
 
Total* $10,561 $2,240 $12,801 $12,801 $12,801 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/19/2012 

09/30/2013 
 

 
06/01/2015 

12/20/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2013 

12/31/2015 
 

03/07/2017 
09/30/2013 

03/02/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2016 

03/31/2016 
03/07/2017 

03/07/2017 
03/31/2017 

12/31/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 20 19
Reduced Operating/Maintenance Cost 25 84

Bond Funding Cost
Adopted:
$3,171,457
Current Approved:
$4,006,921
Actual Expenditures:
$4,006,921

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31