Cropley Single Crossover

Description: VTA requires a new single crossover between Cropley & Montague

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95134
 
Senate District
15
Assembly District 25
Congressional District 19
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFERY BALLOU (408) 321-5628   JEFFERY.BALLOU@VTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$3,003 $1,445 $4,448
PTMISEA-99314
$0 $46 $46
Non-bond Funding
Local**
$600 $-600 $0
 
Total**** $3,603 $891 $4,494

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$600 $-600 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,003 $1,491 $4,494 $4,494 $4,494 $0
 
Total* $3,603 $891 $4,494 $4,494 $4,494 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2018 

08/01/2018 
 

 
06/01/2018 

08/01/2018 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/02/2018 

12/31/2018 
 

08/03/2021 
07/02/2018 

07/31/2021 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2019 

06/30/2021 
 

08/03/2021 
06/01/2019 

07/29/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2021 

12/31/2021 
09/12/2023 

09/12/2023 
06/30/2023 

09/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50

Bond Funding Cost
Adopted:
$3,002,596
Current Approved:
$46,149
Actual Expenditures:
$46,149

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31