Sonoma County Replacement Bus Purchase |
Description: Purchase of five 40 ft., CNG powered replacement transit coaches
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sonoma |
City | Santa Rosa, Ca |
Zip Code | 95407 |
Senate District |
06, 07 |
Assembly District | 02, 03 |
Congressional District | 01, 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Reduced Emissions | 10 | 10 |
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
BRYAN ALBEE | (707) 585-7516 | BKALBEE@SCTRANSIT.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $86 | $86 | ||||
PTMISEA-99313 |
$3,220 | $767 | $3,987 | ||||
PTMISEA-99314 |
$1,090 | $-60 | $1,031 | ||||
Non-bond Funding | |||||||
State/Federal* |
$400 | $3,898 | $4,298 | ||||
Local** |
$0 | $1,044 | $1,044 | ||||
Total**** | $4,710 | $5,736 | $10,446 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,224 | $4,222 | $10,446 | $10,446 | $10,446 | $0 | |
Total* | $4,710 | $5,736 | $10,446 | $10,446 | $10,446 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2010 11/30/2010 |
08/17/2016 08/17/2016 |
08/01/2016 09/30/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2012 03/31/2012 |
08/21/2018 08/21/2018 |
08/31/2018 09/30/2018 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Reduced Emissions | 10 | 10 |
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,310,040 |
Current Approved: |
$5,017,337 |
Actual Expenditures: |
$5,017,337 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31