Caltrans Logo

Elk Grove Automated Farebox Upgrade

Description: Replace existing fareboxes to improve reliability of the bus fleet

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento, Ca
Zip Code 95814
 
Senate District
02
Assembly District 05
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    8  
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GARY TAYLOR (916) 340-6279   GTAYLOR@SACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$3 $0 $3
PTMISEA-99313
$800 $0 $800
PTMISEA-99314
$74 $0 $74
Non-bond Funding
 
Total**** $876 $0 $876

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$876 $0 $876 $874 $874 $3
 
Total* $876 $0 $876 $874 $874 $3

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2011 

11/01/2012 
 

 
12/16/2011 

12/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
 

08/16/2012 
 

12/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 8
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$876,329
Current Approved:
$876,329
Actual Expenditures:
$876,329

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31