Purchase of 2 CNG Cutaway Vehicles

Description: Purchase of two CNG cutaway vehicles for deviated fixed-route service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Joshua Tree
Zip Code 92252
 
Senate District
18
Assembly District 65
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOE MEER (760) 366-2986   JOE@MBTABUS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$183 $0 $183
Non-bond Funding
 
Total**** $183 $2 $184

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$183 $2 $184 $183 $183 $2
 
Total* $183 $2 $184 $183 $183 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2009 

01/01/2011 
08/04/2011 

08/04/2011 
11/01/2009 

03/17/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2011 

02/01/2011 
08/04/2011 

08/04/2011 
03/17/2011 

03/17/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 3 3

Bond Funding Cost
Adopted:
$182,506
Current Approved:
$182,506
Actual Expenditures:
$182,506

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31