CNG Station Upgrade

Description: Upgrade CNG compressor to a 175 hp unit at the Twentynine Palms satellite yard.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Joshua Tree
Zip Code 92252
 
Senate District
18
Assembly District 65
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  60    60  
Reduced Emissions  6    6  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOE MEER (760) 366-2986   JOE@MBTABUS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$172 $0 $172
PTMISEA-99314
$28 $0 $28
Non-bond Funding
 
Total**** $200 $0 $200

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $0 $200 $200 $200 $0
 
Total* $200 $0 $200 $200 $200 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2011 

 
 

 
01/01/2011 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2011 

03/01/2011 
 

 
01/01/2011 

03/01/2011 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2011 

12/01/2011 
08/29/2013 

08/29/2013 
04/19/2012 

06/30/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2012 

03/01/2012 
08/29/2013 

08/29/2013 
06/30/2013 

06/30/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 60 60
Reduced Emissions 6 6
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$200,000
Actual Expenditures:
$200,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31