Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Manteca Fare box Upgrades |
Description: Purchase & installation of 8 automated farebox collection and validation systems to replace the canister fare collection vaults on the Manteca Transit buses.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95202 |
Senate District |
05 |
Assembly District | 12 |
Congressional District | 09 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 30 | 10 |
Increased Ridership | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
RYAN NIBLOCK | (209) 235-0588 | NIBLOCK@SJCOG.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$16 | $-16 | $0 | ||||
PTMISEA-99313 |
$349 | $-24 | $325 | ||||
PTMISEA-99314 |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $17 | $17 | ||||
Total**** | $365 | $-23 | $342 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$365 | $-23 | $342 | $342 | $342 | $0 | |
Total* | $365 | $-23 | $342 | $342 | $342 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2016 06/30/2017 |
05/16/2019 05/16/2019 |
07/01/2017 05/01/2019 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/01/2017 12/31/2017 |
05/16/2019 05/16/2019 |
05/01/2019 06/30/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 30 | 10 |
Increased Ridership | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$365,013 |
Current Approved: |
$325,219 |
Actual Expenditures: |
$325,219 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31