Caltrans Logo

Manteca Fare box Upgrades

Description: Purchase & installation of 8 automated farebox collection and validation systems to replace the canister fare collection vaults on the Manteca Transit buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 12
Congressional District 09
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30    10  
Increased Ridership  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RYAN NIBLOCK (209) 235-0588   NIBLOCK@SJCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$16 $-16 $0
PTMISEA-99313
$349 $-24 $325
PTMISEA-99314
$0 $0 $0
Non-bond Funding
Local**
$0 $17 $17
 
Total**** $365 $-23 $342

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$365 $-23 $342 $342 $342 $0
 
Total* $365 $-23 $342 $342 $342 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2016 

06/30/2017 
05/16/2019 

05/16/2019 
07/01/2017 

05/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2017 

12/31/2017 
05/16/2019 

05/16/2019 
05/01/2019 

06/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30 10
Increased Ridership 5 5

Bond Funding Cost
Adopted:
$365,013
Current Approved:
$325,219
Actual Expenditures:
$325,219

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31