Transit Bus Shelter/Maintenance Facility

Description: Construct a shelter facility to facilitate maintenace of 2 CNG transit vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Ripon
Zip Code 95366
 
Senate District
05
Assembly District 17
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN WERNER (209) 599-0235   KWERNER@CITYOFRIPON.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$450 $0 $450
PTMISEA-99314
$1 $0 $1
Non-bond Funding
State/Federal*
$0 $245 $245
 
Total**** $451 $250 $701

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$451 $250 $701 $701 $701 $0
 
Total* $451 $250 $701 $701 $701 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
03/07/2012 

03/07/2012 
08/01/2012 

01/10/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
03/21/2013 

08/14/2013 
02/01/2013 

12/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2011 

06/30/2011 
08/29/2017 

08/29/2017 
08/01/2016 

06/13/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2011 

09/30/2011 
08/29/2017 

08/29/2017 
06/22/2017 

08/15/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$450,883
Current Approved:
$450,883
Actual Expenditures:
$450,883

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31