Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Facilites and Maintenance Equipment |
Description: Bus Facilities and Maintenance Equipment
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95202 |
Senate District |
05, 14 |
Assembly District | 15, 17, 26 |
Congressional District | |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Reduced Operating/Maintenance Cost | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
DONNA DEMARTINO | (209) 948-5566 X613 | DDEMARTINO@SANJOAQUINRTD.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99314 |
$127 | $-36 | $91 | ||||
Non-bond Funding | |||||||
State/Federal* |
$509 | $719 | $1,228 | ||||
Total**** | $636 | $683 | $1,319 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$636 | $683 | $1,319 | $1,319 | $1,319 | $0 | |
Total* | $636 | $683 | $1,319 | $1,319 | $1,319 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/31/2009 06/30/2011 |
08/26/2011 09/11/2012 |
07/31/2011 06/30/2013 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2011 07/31/2011 |
10/21/2016 10/21/2016 |
09/01/2016 09/30/2016 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Reduced Operating/Maintenance Cost | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$127,163 |
Current Approved: |
$91,361 |
Actual Expenditures: |
$91,361 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31