SLO Transit Bus Radio System Replacement

Description: Replacement of 20 mobile, one base station, and five handheld units for SLO Transit.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City San Luis Obispo
Zip Code 93401
 
Senate District
15
Assembly District 33
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOHN P. WEBSTER (805) 781-7121   JWEBSTER@SLOCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$26 $0 $26
Non-bond Funding
State/Federal*
$184 $0 $184
 
Total**** $210 $0 $210

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$210 $0 $210 $26 $26 $184
 
Total* $210 $0 $210 $26 $26 $184

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2010 

01/01/2011 
03/14/2012 

03/14/2012 
11/01/2011 

06/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2011 

12/31/2011 
08/28/2012 

08/28/2012 
06/30/2012 

06/30/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50

Bond Funding Cost
Adopted:
$25,689
Current Approved:
$25,689
Actual Expenditures:
$25,689

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31