Buellton North Ave of Flags Transit Stop/Park and Ride Construction

Description: Construction of a new park and ride facility with bike lockers, transit stop, transit shelter, lighting and appurtenant facilities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93110
 
Senate District
35
Assembly District 19
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Emissions  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHEN VANDENBURGH (805) 961-8904   SVANDENBURGH@SBCAG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$1 $-1 $0
PTMISEA-99313
$39 $-39 $0
Non-bond Funding
 
Total**** $40 $-40 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$40 $-40 $0 $0 $0 $0
 
Total* $40 $-40 $0 $0 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

12/01/2014 
 

 
07/01/2012 

12/01/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2013 

12/01/2014 
 

02/25/2020 
07/01/2013 

11/01/2019 
95   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2015 

10/01/2015 
11/04/2021 

11/04/2021 
10/01/2022 

03/01/2023 
 

 


Begin Closeout Phase

End Closeout Phase
10/01/2015 

12/01/2015 
11/04/2021 

11/04/2021 
04/01/2023 

06/01/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Emissions 5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31