Caltrans Logo

Transit DAR Shelters for Woodlake

Description: Installation of 3 bus shelters for Dial-A-Ride users

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Visalia
Zip Code 93277
 
Senate District
16, 18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      15  
Increased Ridership  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CHRISTINE CHAVEZ (559) 624-7270   CHCHAVEZ@CO.TULARE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$58 $-11 $47
Non-bond Funding
State/Federal*
$145 $-145 $0
 
Total**** $203 $-156 $47

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$203 $-156 $47 $47 $47 $0
 
Total* $203 $-156 $47 $47 $47 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2010 

02/28/2011 
 

09/14/2011 
11/01/2010 

12/31/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2011 

04/30/2011 
09/14/2011 

09/14/2011 
07/01/2011 

08/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2011 

07/31/2011 
09/14/2011 

09/14/2011 
10/01/2011 

11/30/2011 
 

 


Begin Closeout Phase

End Closeout Phase
08/01/2011 

08/31/2011 
09/14/2011 

09/14/2011 
12/01/2011 

12/31/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Increased Ridership 1

Bond Funding Cost
Adopted:
$57,959
Current Approved:
$46,640
Actual Expenditures:
$46,640

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31