TO Transit - Operations Center Bus Parking |
Description: Construction of a new, dedicated bus parking area at Municipal Service Center to include solar cell covered parking and new CNG fueling terminals.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Ventura |
Zip Code | 93003 |
Senate District |
19 |
Assembly District | 37 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | |
Increased Ridership | 5 | 5 |
Reduced Operating/Maintenance Cost | 10 | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
PETER DEHAAN | (805) 642-1591 X106 | PDEHAAN@GOVENTURA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $4 | $4 | ||||
PTMISEA-99313 |
$150 | $-10 | $140 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $1,559 | $1,559 | ||||
Total**** | $150 | $1,553 | $1,703 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $152 | $152 | $0 | $0 | $152 | |
Design(PS&E) |
$30 | $160 | $190 | $0 | $0 | $190 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$120 | $1,241 | $1,361 | $144 | $144 | $1,217 | |
Total* | $150 | $1,553 | $1,703 | $144 | $144 | $1,559 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2010 11/01/2010 |
|
01/01/2010 11/01/2010 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2011 08/30/2011 |
09/06/2012 04/11/2013 |
01/01/2011 10/30/2011 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2012 02/01/2012 |
04/11/2013 03/20/2014 |
11/04/2012 02/28/2014 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2012 06/30/2012 |
03/20/2014 10/29/2015 |
03/01/2014 07/31/2015 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | |
Increased Ridership | 5 | 5 |
Reduced Operating/Maintenance Cost | 10 | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$150,000 |
Current Approved: |
$140,049 |
Actual Expenditures: |
$140,049 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31