Ventura County Sealed Corridor

Description: Safety improvements along Metrolink service corridor in Ventura County including four-quadrant gates, median separators or raised islands, new signs and pavement markings, etc.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 37
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER DEHAAN (805) 642-1591 X106   PDEHAAN@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$500 $0 $500
Non-bond Funding
State/Federal*
$430 $2,005 $2,435
Local**
$0 $1,633 $1,633
 
Total**** $930 $3,638 $4,568

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$430 $-430 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$500 $4,068 $4,568 $4,568 $4,568 $0
 
Total* $930 $3,638 $4,568 $4,568 $4,568 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2009 

05/01/2009 
 

 
01/01/2009 

05/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/02/2010 

03/11/2011 
 

03/08/2012 
04/02/2010 

12/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/15/2011 

05/04/2012 
04/02/2014 

04/06/2017 
02/22/2013 

11/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
05/05/2012 

07/27/2012 
04/06/2017 

03/08/2019 
12/31/2016 

06/01/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1

Bond Funding Cost
Adopted:
$500,000
Current Approved:
$500,000
Actual Expenditures:
$500,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31