Caltrans Logo

Replacement 35 foot bus

Description: Replace aging equipment with 35 foot bus, low floor, ADA accessable, 32 passenger diesel powered transit bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Humboldt
City Arcata
Zip Code 95521
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25      
Reduced Emissions  25      
Reduced Operating/Maintenance Cost  75    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LARRY PARDI (707) 822-3775   LPARDI@CITYOFARCATA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$200 $680 $880
PTMISEA-99314
$19 $42 $61
Non-bond Funding
 
Total**** $219 $729 $948

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$219 $729 $948 $948 $948 $0
 
Total* $219 $729 $948 $948 $948 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2011 

06/30/2012 
09/26/2014 

09/26/2014 
08/23/2013 

05/16/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
09/26/2014 

09/26/2014 
04/30/2014 

05/16/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25
Reduced Emissions 25
Reduced Operating/Maintenance Cost 75 25

Bond Funding Cost
Adopted:
$219,006
Current Approved:
$941,159
Actual Expenditures:
$941,159

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31